Abstrak

The modeling and design of grid-connected floating photovoltaic (PV) are covered in this paper. Using dams in West Java as a location with present floating PV potential, this paper encourages the development of renewable energy and the construction of fossil-free power plants in various parts of Indonesia. Three alternative locations —the Saguling, Cirata, and Jatiluhur dams —are proposed for floating-PV type designs, each having a capacity of 1 MW grid-connected. The modeling process uses a variety of dependable auxiliary software to simulate possible solar energy use as well as capacity design optimization of system components. Modeling and simulation findings indicate that the grids of the Saguling, Cirata, and Jatiluhur dam have a combined potential for electrical energy of 1705.2 MWh/year, 1635.4 MWh/year, and 1611.8 MWh/year, respectively, with an average performance ratio of 0.74 to 0.75. The total PV capacity for each dam is 1197 Wp, using 550 Wp/PV panel with an efficiency 21.51%/PV and 4 Inverters for grid connectivity. There are 544 PV units per array. 5561 m2 is the estimated area needed to build this system.

Keyword: Cirata, floating PV, Jatiluhur, performance ratio, Saguling


Ketersediaan

Tidak ada salinan data


Informasi Detail

Judul Seri
-
No. Panggil
-
Penerbit Department of Electrical Engineering, Politeknik Negeri Padang : Padang.,
Deskripsi Fisik
-
Bahasa
English
ISBN/ISSN
2654-4733
Klasifikasi
NONE
Tipe Isi
text
Tipe Media
-
Tipe Pembawa
-
Edisi
vol 15, No. 2, tahun 2023
Subjek
-
Info Detail Spesifik
-
Pernyataan Tanggungjawab

Versi lain/terkait

Tidak tersedia versi lain


Lampiran Berkas



Informasi


Akses Katalog Publik Daring - Gunakan fasilitas pencarian untuk mempercepat penemuan data katalog